MoRTH executed highway projects at a rate of 28.16km/day between April 1, 2020 to January, 15, 2021, which is around 8 percent (Y-o-Y)  higher.
The government had awarded 7,597km of national highways till January 15, 2021 as against the target award of 4,500km for FY2021 with the award speed of 26.2 km/day.
Pace of highway construction across India picks up in January

According to the Ind-Ra note, the targeted construction of 11,000km for FY2021 could be achieved, considering that the environment is conducive for construction activities in Q4FY2021.

29 Jan 2021 | 15720 Views | By Shahkar Abidi

With infrastructure activities picking up pace, the rate of highway construction has increased to 76.3km/day between January 8-15. This is better than the Ministry of Road Transport & Highways’ overall target of constructing 60,000 km of national highways by FY2024, which would require a minimum execution pace of 33 ...